Laboratory Gas Systems at The Francis Crick Institute

 

Francis Crick

 

Medical Gases is proud to have been awarded a contract worth over £2m for the installation of the laboratory gas systems at The Francis Crick Institute in London. The scope of work includes the installation of more than 15000m of high purity distribution pipework and 125 cylinder gas manifold stations to over 1000 terminal units. The Institute is scheduled to open in 2015. When it is fully operational it will house some 1500 staff, making it one of Europe’s largest centres of biomedical research and innovation.

Project: UKCMRI – Francis Crick Institute

Client: Crown House Technologies

Value:  £2,100,000